Question: Activity Predecessor Time ( days ) A - - 8 B - - 6 C - - 3 D A , B 1 0 E

Activity Predecessor Time (days)
A --8
B --6
C --3
D A,B 10
E C 8
F A 5
G D,E 3
H G 4
Using Table 7.5, every day the construction crew is on-site costs $1000. What activities would you consider crashing to reduce the project completion cost?
Activity E
Activity F
Activity G
All of these activities would be candidates for crashing.