Question: Using Tables below, compare and contrast the Planned Shipment Schedule if the Distribution Requirements Plan is made using initially normal DRP process and then with

Using Tables below, compare and contrast the Planned Shipment Schedule if the Distribution Requirements Plan is made using initially normal DRP process and then with the Error Add Back consideration. Notes: Actual Demand for Period 1, 2, and 3 were 250, 335 \\& 215 respectively. Forecast requirements for each Time period are 265 units, there are currently 185 units to hand and 200 units are due to arrive in Wk 1. There is a safety stock requirement of 65 units, with a lead time of 1 week. Quantities are supplied (shipped) in a lot for lot basis
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
