Question: Using the activity list below and an appropriate drawing tool, create a complete network diagram using the precedence method showing Activity, Duration, Early and Late
Using the activity list below and an appropriate drawing tool, create a complete network diagram using the precedence method showing Activity, Duration, Early and Late Start, Early and Late Finish and Slack:
| Activity | Duration | Predecessor |
| A | 5 | - |
| B | 12 | A |
| C | 20 | B |
| D | 15 | B |
| E | 15 | B |
| F | 30 | C,D |
| G | 12 | E,F |
| H | 8 | G |