Question: using the activity-on-arrow (AOA) method, and problem. Draw a corresponding AOA network. Compute ES and EF for each activity. Compute LS and LF for each

using the activity-on-arrow (AOA) method, and

  1. using the activity-on-arrow (AOA) method, and problem. Draw a corresponding AOA network.

Compute ES and EF for each activity.

Compute LS and LF for each activity.

Find the critical path.

Determine the total slack and free slack.

a. Predecessor Duration 6 Activity A . 3 A 9 D B 5 E B 4 F D 2 G E 8