Question: Using the assembly-line balancing procedure, what is the required workstation cycle time if the production time in minutes per day is 420 and the required
Using the assembly-line balancing procedure, what is the required workstation cycle time if the production time in minutes per day is 420 and the required output per day in units is 2000? (Use minute as a unit. Keep two decimal points!)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
