Question: Using the below table calculate critical path for the project. Which tasks are on the critical path? Task Predecessor Duration (Weeks) A 32 B
Using the below table calculate critical path for the project. Which tasks are on the critical path? Task Predecessor Duration (Weeks) A 32 B 21 C 12 D B,C 16 E A,B 23 F A 23 G D 34 H D 33 A D E F G H