Question: Using the below table calculate critical path for the project. Which tasks are on the critical path? Task Predecessor Duration (Weeks) A 32 B

Using the below table calculate critical path for the project. Which tasks

Using the below table calculate critical path for the project. Which tasks are on the critical path? Task Predecessor Duration (Weeks) A 32 B 21 C 12 D B,C 16 E A,B 23 F A 23 G D 34 H D 33 A D E F G H