Question: Using the below table calculate critical path for the project. Which tasks are on the critical path? Task Predecessor Duration ( Weeks ) A -

Using the below table calculate critical path for the project. Which tasks are on the critical path?
Task Predecessor Duration (Weeks)
A -
12
B -15
C A,B 12
D A 13
E -13
F C 13