Question: Raquel is concerned with efficiency. She believes it is probably more efficient to use SPT (shortest processing time) as her priority rule. (a) Develop a

Raquel is concerned with efficiency. She believes it is probably more efficient to use SPT (shortest processing time) as her priority rule.

(a) Develop a sequence using SPT based on processing time for preparing the area.

(b) Calculate the makespan, the mean job flow time, and the average number of jobs in the system.


Step by Step Solution

3.43 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Prepare Plant b Make span 31 days Mean job ... View full answer