Question: Using the CPM approach to Project Management, what is the critical path and completion time for the for following network diagram? table [ [

Using the CPM approach to Project Management, what is the critical path and completion time for the for following network diagram?
\table[[ACTIVITY,Precedent Activity,Completion Time (days)],[A,NONE,1],[B,A,1],[C,B,2],[D,C,3],[E,D,4],[F,E,5],[G,E,4],[H,F, G,],[A-B-C-D-E-F-H =17 days,,],[A-B-C-D-E-G-H =16 days,,],[A-B-C-D-E-F-G-H =22 days,,],[A-B-C-D-E-F-H =19 days,,],[A-B-C-D-E-G-H =19 days,,]]
 Using the CPM approach to Project Management, what is the critical