Question: Using the CPM approach to Project Management, what is the critical path and completion time for the for following network diagram? ACTIVITY Precedent Activity Completion
Using the CPM approach to Project Management, what is the critical path and completion time for the for following network diagram?
| ACTIVITY | Precedent Activity | Completion Time (days) |
| A | NONE | 1 |
| B | A | 1 |
| C | B | 2 |
| D | C | 3 |
| E | D | 4 |
| F | E | 5 |
| G | E | 4 |
| H | F, G | 1 |
| A-B-C-D-E-F-H = 17 days | ||
| A-B-C-D-E-G-H = 16 days | ||
| A-B-C-D-E-F-G-H = 22 days | ||
| A-B-C-D-E-F-H = 19 days | ||
| A-B-C-D-E-G-H = 19 days |