Question: Using the CPM approach to Project Management, what is the critical path and completion time for the for following network diagram? ACTIVITY Precedent Activity Completion
| Using the CPM approach to Project Management, what is the critical path and completion time for the for following network diagram?
|
| A-B-C-D-F-G-H-I = 19 days | ||
| A-B-C-E-H-1 = 15 days | ||
| A-B-C-D-E-F-G-H-I = 24 days |