Question: using the data below create a time-phased budget for the project. Show how much daily and cumulative costs of a project is, just as monthly
using the data below create a time-phased budget for the project. Show how much daily and cumulative costs of a project is, just as monthly and cumulative costs are shown in figure 10.
| WBS | Activity | Intermediate Predecessor | Duration in Weeks | Resource | Hourly cost | Hours per week |
| 1 | Operational definition |
|
|
|
|
|
| 1.1 | Research literature |
| 3 | Becky | $35 | 30 |
| 1.2 | Identify and define terms | 1.1 | 1 | Ann | $60 | 30 |
| 1.3 | Obtain approval of definition | 1.2 | 2 | Clive | $50 | 30 |
| 2 | Target selection |
|
|
|
|
|
| 2.1 | Solicit partners for pilot. |
| 2 | Ann |
|
|
| 2.2 | Hold brainstirming meeting | 2.1 | 2 | Becky |
|
|
| 2.3 | Identify characteristics of targets. | 2.2,3.1 | 1 | Ann |
|
|
| 2.4 | Obtain approval of partners | 2.3,1.2,3.4 | 1 | Clive |
|
|
| 3 | Question Set |
|
|
|
|
|
| 3.1 | Identify Process group members |
| 2 | Clive |
|
|
| 3.2 | Develop question set | 2.3 | 4 | Ann |
|
|
| 3.3 | Prototype and valid question set | 3.2 | 3 | Becky |
|
|
| 3.4 | Add partners | 3.1,2.1 | 3 | Becky |
|
|