Question: using the data below create a time-phased budget for the project. Show how much daily and cumulative costs of a project is, just as monthly

using the data below create a time-phased budget for the project. Show how much daily and cumulative costs of a project is, just as monthly and cumulative costs are shown in figure 10.

WBS

Activity

Intermediate

Predecessor

Duration in

Weeks

Resource

Hourly

cost

Hours per

week

1

Operational definition

1.1

Research literature

3

Becky

$35

30

1.2

Identify and define terms

1.1

1

Ann

$60

30

1.3

Obtain approval of definition

1.2

2

Clive

$50

30

2

Target selection

2.1

Solicit partners for pilot.

2

Ann

2.2

Hold brainstirming meeting

2.1

2

Becky

2.3

Identify characteristics of targets.

2.2,3.1

1

Ann

2.4

Obtain approval of partners

2.3,1.2,3.4

1

Clive

3

Question Set

3.1

Identify Process group

members

2

Clive

3.2

Develop question set

2.3

4

Ann

3.3

Prototype and valid question set

3.2

3

Becky

3.4

Add partners

3.1,2.1

3

Becky

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!