Question: Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days,
Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days, and so on until it is in an all-crash mode. Identify how much it would cost for each day you crash the schedule.

\begin{tabular}{|c|l|c|c|c|c|c|} \hline Activity & Predecessor & Normal Time & Normal Cost & Crash Time & Crash Cost & Crash Cost per Day \\ \hline A & - & 12 & 200 & 9 & 350 & \\ \hline B & A & 8 & 300 & 8 & 300 & \\ \hline C & A & 9 & 250 & 7 & 450 & \\ \hline D & B & 6 & 400 & 5 & 600 & \\ \hline E & B, C & 5 & 150 & 4 & 225 & \\ \hline F & C & 10 & 500 & 9 & 650 & \\ \hline G & D, E, F & 8 & 400 & 6 & 900 & \\ \hline \end{tabular}