Question: Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days,

Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days, and so on until it is in an all crash mode. Identify how much it would cost for each day you crash the schedule. (IN DETAILS PLEASE)

Activity

Predecessor

Normal time

Normal cost

Crash time

Crash cost

crash cost per day

A

-

12

200

9

350

B

A

8

300

8

300

C

A

9

250

7

450

D

B

6

400

5

600

E

B,C

5

150

4

225

F

C

10

500

9

650

G

D,E,F

8

400

6

900

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!