Question: Using the data for Project S and Project T below, conduct an Incremental IRR Analysis and select the correct answer. MARR is 1 0 %

Using the data for Project S and Project T below, conduct an Incremental IRR Analysis and select the correct answer. MARR is 10% per year.
\table[[,S,T],[First Cost,-50,000,-75,000
Using the data for Project S and Project T below,