Question: Using the data in the table below, what is the latest possible time that C may be started without delaying completion of the project? Activity:

Using the data in the table below, what is the latest possible time that C may be started without delaying completion of the project?
Activity: a,b,c,d,e,f
Immediate Predecessor: -,-,a,b,c/d,b
Time: 4,3,2,7,4,5