Question: Table 1 1 - 4 The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time A -

Table 11-4
The following represents a project with known activity times. All times are in weeks.
Activity Immediate
Predecessor Time
A --4
B --3
C A 2
D B 7
E C, D 4
F B 5
G E, F 4
Using the data in Table 11-4, what is the latest possible time that C may be started without delaying completion of the project?