Question: Using the data provided in the attached MS Excel file, create the project schedule in MS Project. Create new project in MS Project. Set the

Using the data provided in the attached MS Excel file, create the project schedule in MS Project.
Create new project in MS Project.
Set the title of the project to Marketing Project. Make sure you are the author. Set the start date to todays date. (Ch 3)
Copy and paste or type in the activities as listed in the Excel file.
Add the WBS column to the Gantt view (Ch.7)
Create the WBS structure by creating summary tasks (Ch 7)
Add project summary task (Ch 3)
Add Durations per the Excel file (Ch 8) Note: Make sure you set the duration to Weeks!
Set the Timescale to Weeks
Add Predecessors per the Excel file (Ch 8)
Identify the critical path (Ch 8)
Add resources per the Excel file. Chapter 9 covers this, but the easiest way to do this is simply to type the names in the Resource Names column.
Using the Resource Sheet (Ch 9), add a Std. Rate and an Ovt. rate for each resource. (You choose the rates.)
Return to the Gantt chart page.
Use the Split View to show both the Gantt chart with critical path and resource graph or resource usage.
Save your MS Project file.
Using your own MS Project file, create a Word document and answer the following questions:
Which tasks are on the critical path?
Which resources are overloaded?
Briefly explain two ways you might resolve the overloads.
What is the estimated cost of your project?
Submit both documents to the assignment link.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!