Question: Using the FCFS method, determine the (a) job sequence (b) flow time, (c) average tardiness, and (d) number of jobs at the work center JOB
Using the FCFS method, determine the
(a) job sequence
(b) flow time,
(c) average tardiness, and
(d) number of jobs at the work center
JOB PROCESSING TIME (DAYS) DUE DATE
A 14 4
B 25 12
C 10 10
D 25 20
E 10 15