Question: Using the figure BELOW, perform resource-limited scheduling . Assume that you have only two workers available at any given time. Task 1 (1 worker) 1
Using the figure BELOW, perform resource-limited scheduling. Assume that you have only twoworkers available at any given time.

Task 1 (1 worker) 1 Task 2 (1 worker) Task 3 (2 workers) 2 Task 4 (1 worker) 1 Task 5 (2 workers) 2 Day 1 2 4 5 6 7 8 Workers 2 2 5 4 2 3 3