Question: Using the following data what are the te and variance (respectively) for activity A? Activity A Optimistic = 2 days, Most likely = 5 days,

Using the following data what are the te and variance (respectively) for activity A? Activity A Optimistic = 2 days, Most likely = 5 days, Pessimistic = 9 days

5.167, 1.361

.167, 1.166

None of these are correct

2.67, 1.361

2.67, 1.166