Question: Using the following information about work package budgets, complete the overall time-phased budget for the following project. Which weeks have the greatest budget expense? TASK
- Using the following information about work package budgets, complete the overall time-phased budget for the following project. Which weeks have the greatest budget expense?
| TASK | Budget | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 |
| A | 5 | 3 | 2 |
|
|
|
|
|
|
| B | 9 | 1 | 4 | 3 | 1 |
|
|
|
|
| C | 12 |
| 2 | 7 | 3 |
|
|
|
|
| D | 7 |
|
| 3 | 3 | 1 |
|
|
|
| E | 14 |
|
|
| 5 | 5 | 2 | 2 |
|
| F | 6 |
|
|
|
|
| 1 | 2 | 3 |
| Plan | 53 | 4 | 8 |
|
|
|
|
|
|
| Cumulative |
| 4 | 12 |
|
|
|
|
|
|