Question: Using the following table, calculate the project duration Task Predecessor Duration ( days ) A - 5 7 B A 3 6 C - 4

Using the following table, calculate the project duration
Task Predecessor Duration (days)
A -57
B A 36
C -46
D -19
E B 30
F B,C 18
G E,F 43
H F 23