Question: Using the following table, calculate the project duration Task Predecessor Duration (weeks) A - 1 B A 2 C - 2 D - 8 E

Using the following table, calculate the project duration

Task Predecessor Duration (weeks)
A - 1
B A 2
C - 2
D - 8
E B 2
F C, B 2
G E,F 2
H D,F 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!