Question: Using the following table, calculate the project duration Task Predecessor Duration (weeks) A - 1 B A 2 C - 2 D - 8 E
Using the following table, calculate the project duration
| Task | Predecessor | Duration (weeks) |
| A | - | 1 |
| B | A | 2 |
| C | - | 2 |
| D | - | 8 |
| E | B | 2 |
| F | C, B | 2 |
| G | E,F | 2 |
| H | D,F | 8 |