Question: using the following table, calculate the project duration Task Predecessor Duration (days) A - 84 B A 51 C - 22 D - 19 E
using the following table, calculate the project duration
| Task | Predecessor | Duration (days) |
| A | - | 84 |
| B | A | 51 |
| C | - | 22 |
| D | - | 19 |
| E | B | 27 |
| F | B,C | 48 |
| G | E,F | 46 |
| H | F | 19 |