Question: using the following times for activity A, the expected completion time for activity A is: Activity Optimistic Most Likely Pessimistic A 15 22 35 A.
using the following times for activity A, the expected completion time for activity A is:
Activity Optimistic Most Likely Pessimistic
A 15 22 35
A. 23
B. 24
C. 22
D. None of the above
E. 21
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts