Question: using the following times for activity A, the expected completion time for activity A is: Activity Optimistic Most Likely Pessimistic A 15 22 35 A.

using the following times for activity A, the expected completion time for activity A is:

Activity Optimistic Most Likely Pessimistic

A 15 22 35

A. 23

B. 24

C. 22

D. None of the above

E. 21