Question: Using the high-low method, calculate variable utilities costs per machine hour. Month Cost Machine Hours January $ 8,100 13,900 February 14,500 20,500 March 7,500 10,500
Using the high-low method, calculate variable utilities costs per machine hour.
| Month | Cost | Machine Hours |
|---|---|---|
| January | $ 8,100 | 13,900 |
| February | 14,500 | 20,500 |
| March | 7,500 | 10,500 |
| April | 9,200 | 18,900 |
a. $0.50
b. $0.25
c. $0.70
d. $0.63
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts