Question: Using the information below, determine the average flow time for MST. Job Processing Time (days) Due Date (days) A 4 11 B 6 5 C

Using the information below, determine the average flow time for MST.

Job

Processing Time (days)

Due Date (days)

A

4

11

B

6

5

C

3

1

D

2

8

E

5

7

Multiple Choice

  • 11.2

  • 12.5

  • 10

  • 12.4