Question: Using the information from the same project: Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost A - 4 3 100 350 B A

Using the information from the same project:

Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost
A - 4 3 100 350
B A 3 2 250 425
C A 2 2 400 400
D C 5 2 150 600
E B 3 3 325 325
F D, E 6 4 225 775
G D 4 2 175 925
H F, G 2 2 550 550

What is the late finish time for Activity B?

Group of answer choices

3

10

11

17

None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!