Question: Using the information from the same project: Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost A - 4 3 100 350 B A
Using the information from the same project:
| Activity | Predecessor | Normal Time | Crash Time | Normal Cost | Crash Cost |
| A | - | 4 | 3 | 100 | 350 |
| B | A | 3 | 2 | 250 | 425 |
| C | A | 2 | 2 | 400 | 400 |
| D | C | 5 | 2 | 150 | 600 |
| E | B | 3 | 3 | 325 | 325 |
| F | D, E | 6 | 4 | 225 | 775 |
| G | D | 4 | 2 | 175 | 925 |
| H | F, G | 2 | 2 | 550 | 550 |
What is the late finish time for Activity B?
Group of answer choices
3
10
11
17
None of the above