Question: Using the information given, do the following: (i) Draw the precedence network diagram. (ii) Identify the critical path. (iii) Determine expected project duration. Activity

Using the information given, do the following: (i) Draw the precedence network diagram. (ii) Identify the critical path. (iii) Determine expected project duration. Activity Start a d f b e C h 6.0.1 i Precedes a,b,c d f g 6.D f h g,i end end Duration 562 V 5 9 4 6 3 1
Step by Step Solution
There are 3 Steps involved in it
To draw the precedence network diagram well use the activityonnode AON method Heres the diagr... View full answer