Question: Using the information in tablc given below, assuming that the project team wil work a standard working week (5 working days in 1 week) and
Using the information in tablc given below, assuming that the project team wil work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible. Task Description Duration Dependencies davs A Requirement Analysis None System Desi 15 25 15 30 10 10 C Programmin D Telcom E Hardware installation Integration C,D E,F G System Testin H Training/Support Handover/Go Live a) Define project scheduling. (2 marks) (10 marks) c) Define ANY ONE of the graphical visualization of project schedules. (3 marks) d) Determine the critical path of the project. Mention in number of days and number of b) Draw activity network diagram weeks. Show the method of working (10 marks)