Question: Using the information in the table below, assuming that the project team will work a standard working week ( 5 working days in 1 week
Using the information in the table below, assuming that the project team will work a standard
working week working days in week and that all tasks will start as soon as possible:
Task Description Duration
Working Days
Predecessors
A Requirement Analysis
B Systems Design A
C Programming B
D Telecoms B
E Hardware Installation B
F Integration C D
G System Testing E F
H Documentation G
I TrainingSupport H
J Handover and GoLive H
K Maintenance I, J
Determine the critical path of the project.
Calculate the planned duration of the project in weeks.
Identify any noncritical tasks and the float free slack on each.