Question: Using the information in the table below, assuming that the project team will work a standard working week ( 5 working days in 1 week

Using the information in the table below, assuming that the project team will work a standard
working week (5 working days in 1 week) and that all tasks will start as soon as possible:
Task Description Duration
(Working Days)
Predecessor/s
A Requirement Analysis 4-
B Systems Design 12 A
C Programming 20 B
D Telecoms 6 B
E Hardware Installation 23 B
F Integration 7 C, D
G System Testing 13 E, F
H Documentation 2 G
I Training/Support 5 H
J Handover and Go-Live 3 H
K Maintenance 3 I, J
2.1 Determine the critical path of the project. (8)
2.2 Calculate the planned duration of the project in weeks. (4)
2.3 Identify any non-critical tasks and the float (free slack) on each. (

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!