Question: QUESTION TWO [ 1 5 ] Using the information in the table below, assuming that the project team will work a standard working week (

QUESTION TWO [15]
Using the information in the table below, assuming that the project team will work a standard
working week (5 working days in 1 week) and that all tasks will start as soon as possible:
Task Description Duration
(Working Days)
Predecessor/s
A Requirement Analysis 4-
B Systems Design 12 A
C Programming 20 B
D Telecoms 6 B
E Hardware Installation 23 B
F Integration 7 C, D
G System Testing 13 E, F
H Documentation 2 G
I Training/Support 5 H
J Handover and Go-Live 3 H
K Maintenance 3 I, J
2.1 Determine the critical path of the project. (8)
2.2 Calculate the planned duration of the project in weeks. (4)
2.3 Identify any non-critical tasks and the float (free slack) on each. (3)
QUESTION THREE [15]
Tabulate a risk assessment for the school building project by identifying five(5) risks of your
choice, analyse each risk in terms of the likelihood of it occurring and the severity of impact,
and provide a risk response to each risk. For the analysis of risk you can show the matrix
used to assess the likelihood and severity.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!