Question: QUESTION TWO [ 1 5 ] Using the information in the table below, assuming that the project team will work a standard working week (
QUESTION TWO
Using the information in the table below, assuming that the project team will work a standard
working week working days in week and that all tasks will start as soon as possible:
Task Description Duration
Working Days
Predecessors
A Requirement Analysis
B Systems Design A
C Programming B
D Telecoms B
E Hardware Installation B
F Integration C D
G System Testing E F
H Documentation G
I TrainingSupport H
J Handover and GoLive H
K Maintenance I, J
Determine the critical path of the project.
Calculate the planned duration of the project in weeks.
Identify any noncritical tasks and the float free slack on each.
QUESTION THREE
Tabulate a risk assessment for the school building project by identifying five risks of your
choice, analyse each risk in terms of the likelihood of it occurring and the severity of impact,
and provide a risk response to each risk. For the analysis of risk you can show the matrix
used to assess the likelihood and severity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock