Question: Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1 week) and

Using the information in the table below, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: 4.1 Determine the critical path of the project. (6 marks) 4.2 Calculate the planned duration of the project in weeks. (6 marks) 4.3 Identify any non-critical tasks and the float (free slack) on each. (8 marks)