Question: Using the information in the table below, calculate the total maximum risk contingency for the project. You may fill in the blank cells in
Using the information in the table below, calculate the total maximum risk contingency for the project. You may fill in the blank cells in the table to help you with your calculations. Suppose that you had decided to simply estimate the risk contingency as 5% of the total base cost. Would you have overestimated or underestimated the appropriate amount of contingency compared the result from the expected net risk calculation? Element Clearing Excavation Compaction Handwork Landscaping Paving Base Max Cost Cost $3,694 $4,000 $21,296 $23,000 $2,945 $3,500 $1,750 $2,000 $8,722 $9,500 $105,633 $110,000 Max Risk % Probability 20% 20% 10% 5% 30% 40% Expected Net Risk