Question: Using the information provided in Table 2, perform resource-leveling. Assume that each task can be performed independently of the other tasks, and the project must

  1. Using the information provided in Table 2, perform resource-leveling. Assume that each task can be performed independently of the other tasks, and the project must be completed in 10 days

Table 2

Activity # Activity Name IP Duration (D) Required Resources
1 A1 - 4 2
2 A2 - 3 1
3 A3 - 3 3
4 A4 - 4 2
5 A5 - 3 1
6 A6 - 3 3

Activity Req. Res. D Total Res. Days
A1 2 4
A2 1 3
A3 3 3
A4 2 4
A5 1 3
A6 3 3
Day =>
Total Resources =>

2.Use the information provided for a construction project in Table 3 to develop a resource-constrained plan. Assume that only three workers are available for each day.

Table 3

Activity # IP Duration (D) Required Resources
1 - 4 1
2 - 5 2
3 1 4 2
4 1,2 5 1
5 2 3 2
6 3, 4, 5 2 2

ID Req. Res. D Slack 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 1 4
2 2 5
3 2 4
4 1 5
5 2 3
6 2 2
Total Res. Load
Res. Available

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!