Question: Using the information provided in the table and the network diagram, you will see the project completion time = 25 weeks. You are asked to
Using the information provided in the table and the network diagram, you will see the project completion time = 25 weeks.
You are asked to reduce the completion time of the project by 3 weeks in the most economical way. What will be the total cost of reducing the completion time of the project?
Activity Normal Time (weeks) Normal Cost ($) Crash Time (weeks) Crash Cost ($) Maximum weeks Reduced Crash Cost per Week ($)
A 3 500 2 900 1 400
B 4 600 3 700 1 100
C 6 800 3 1,300 3 166.67
D 6 1,500 4 2,150 2 325
E 6 1,750 4 2,250 2 500
F 5 200 5 1,200 0 0
G 7 1500 5 1,800 2 150
H 3 500 3 0 0 0
16-9
Select one:
a. $450
b. $300
c. $466.67
d. $0
e. $483.34