Question: Using the information provided in the table below, follow the instruction and clearly provide an answer to the following questions: Draw the project network using

Using the information provided in the table below, follow the instruction and clearly provide an answer to the following questions:

Draw the project network using the AON approach. Use a START and/or END nodes as needed.

Using the normal times and normal costs:

Calculate the ES, EF, LS and LF of each activity.

What is the normal (duration) time of the project?

Calculate and show in the nodes of your AON project network the total slack of the non-critical activities.

What are the critical activities and the critical path?

Activity Predecessor

Normal time

(days)

A - 4
B A 9
C B 4
D A 7
E D 4
F D 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!