Question: Using the information provided in the table below, follow the instruction and clearly provide an answer to the following questions: a. Draw the project network

Using the information provided in the table below, follow the instruction and clearly provide an answer to the following questions: a. Draw the project network using the AON approach. Use the START and END node. b. Using the normal times: - Calculate the ES, EF, LS and LF of each activity. - What is the normal (duration) time of the project? - Calculate and show in the nodes of your AON project network (not in a separate place/table) the total slack of the non-critical activities. - What are the critical activities and the critical path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts