Question: Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project

Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 5 weeks in the most economical way.

Activity

Normal Time
(weeks)

Normal
Cost ($)

Crash Time
(weeks)

Crash
Cost ($)

Maximum
Weeks
Reduced

Crash Cost
per Week ($)

A

355029301380

B

46503740190

C

680031,3103170

D

61,50042,1402320

E

61,75042,2502250

F

5200520000

G

71,40051,6902145

H

3500350000

B(4) E(6) A(3) C(6) G(7) H(3) D(6) F(5)


AON network diagram

(If there is no amount for a box enter 0. All boxes must be filled.)

Reduce A by ____________a number of weeks week(s), B by ---------- a number of weeks week(s), C by --------------- a number of weeks week(s), D by ----------------a number of weeks week(s), E by --------------- a number of weeks week(s), F by ----------------- a number of weeks week(s), G by ------------ a number of weeks week(s), H by ------------- a number of weeks week(s).
Total additional cost is $enter total additional cost in dollars
 

B(4) E(6) A(3) C(6) G(7) H(3) D(6) F(5)

Step by Step Solution

3.37 Rating (175 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Steps for crashing a project 1 select the critical path and find the process with the least cost ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!