Using the information provided in the table, the network diagram and the project completion time = 25
Question:
Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 5 weeks in the most economical way.
Activity | Normal Time | Normal | Crash Time | Crash | Maximum | Crash Cost |
---|---|---|---|---|---|---|
A | 3 | 550 | 2 | 930 | 1 | 380 |
B | 4 | 650 | 3 | 740 | 1 | 90 |
C | 6 | 800 | 3 | 1,310 | 3 | 170 |
D | 6 | 1,500 | 4 | 2,140 | 2 | 320 |
E | 6 | 1,750 | 4 | 2,250 | 2 | 250 |
F | 5 | 200 | 5 | 200 | 0 | 0 |
G | 7 | 1,400 | 5 | 1,690 | 2 | 145 |
H | 3 | 500 | 3 | 500 | 0 | 0 |
AON network diagram
(If there is no amount for a box enter 0. All boxes must be filled.)
Reduce A by ____________a number of weeks week(s), B by ---------- a number of weeks week(s), C by --------------- a number of weeks week(s), D by ----------------a number of weeks week(s), E by --------------- a number of weeks week(s), F by ----------------- a number of weeks week(s), G by ------------ a number of weeks week(s), H by ------------- a number of weeks week(s).
Total additional cost is $enter total additional cost in dollars