Question: Using the information provided in the table, the network diagram and the project completion time = 2 7 weeks, calculate the minimum time for completing
Using the information provided in the table, the network diagram and the project completion time weeks, calculate the minimum time for completing the project possible.
tableActivitytableNormalTimeweekstableNormalCost$tableCrashTimeweekstableCrashCost$tableMaximumweeksReducedtableCrashCost perWeek $ABCDEFGH
AON network diagram:
Minimum project completion time weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
