Question: Using the information provided in the table, the network diagram and the project completion time = 26 weeks, calculate the minimum time for completing the
Using the information provided in the table, the network diagram and the project completion time = 26 weeks, calculate the minimum time for completing the project possible.
| Activity | Normal Time (weeks) | Normal Cost ($) | Crash Time (weeks) | Crash Cost ($) | Maximum weeks Reduced | Crash Cost per Week ($) | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A | 2 | 500 | 1 | 900 | 1 | 400 | ||||||
| B | 4 | 600 | 3 | 700 | 1 | 100 | ||||||
| C | 6 | 800 | 3 | 1,300 | 3 | 167 | ||||||
| D | 6 | 1,500 | 4 | 2,150 | 2 | 325 | ||||||
| E | 6 | 1,750 | 4 | 2,250 | 2 | 250 | ||||||
| F | 5 | 1,200 | 5 | 1,200 | 0 | 0 | ||||||
| G | 8 | 1,500 | 6 | 1,800 | 2 | 150 | ||||||
| H | 4 | 500 | 4 | 500 | 0 | 0 |
AON network diagram:
Minimum project completion time = ___________ weeks weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
