Question: Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate ACTIVITY EARLIEST EARLIEST LATEST LATEST Predecessor

Using the information shown in the table below,
Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate ACTIVITY EARLIEST EARLIEST LATEST LATEST Predecessor TIME START FINISH START FINISH SLACK A 2 0 0 2 B 1 2 3 3 4 0 1 0 3 2 5 None A A B B, C DE, F 2 4 D E F 7 5 11 11 3 3 5 5 11 10 8 11 15 5 11 0 G 11 15 0 07 06 O8 05