Question: Using the network below and the additional information provided, find: (a) The crash cost per day per activity. (b) Which activities should be crashed to
Using the network below and the additional information provided, find: (a) The crash cost per day per activity. (b) Which activities should be crashed to meet a project deadline of
| 10 days | at minimum cost. |
(c) Find the new cost.
| Normal Time | Normal | Crashed Cost Crashed |
Time
| Activity | (days) | Cost | (total) | (days) |
| A | 7 | $300 | $700 | 3 |
| B | 3 | 250 | 600 | 1 |
| C | 6 | 500 | 900 | 5 |
| D | 3 | 200 | 500 | 2 |
| E | 2 | 300 | 400 | 1 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts