Question: Using the network above and the additional information below, find: ( a ) The crash cost per day ( b ) Which activities should be

Using the network above and the additional information below, find:
(a) The crash cost per day
(b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost. Assume partial crashing is allowed.
\table[[Activity,\table[[Crash],[Time],[(days)]],\table[[Crashed],[Cost],[(total)]],\table[[Normal],[Time],[(days)]],\table[[Normal],[Cost]]],[A,3,$500,4,$300
 Using the network above and the additional information below, find: (a)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!