Question: Using the network below and the additional information provided, find: (a) The crash cost per day per activity. (b) Which activities should be crashed to
Using the network below and the additional information provided, find: (a) The crash cost per day per activity. (b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost. (C) Find the new cost. B E 4 D 3 Normal Time Normal Crashed Cost Crashed Time Activity _(days) Cost (total) (days) A B 7 3 6 3 1 $300 250 500 200 300 $700 600 900 500 400 0 2
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts