Question: Using the PERT formula, calculate the time ( t ) for each activity. QUESTION 4 4 . 1 The following table represents data of a
Using the PERT formula, calculate the time t for each activity. QUESTION The following table represents data of a project you are working on: Most Optimistic Most likely Activity Predecessor Most Pessimistic Time in days H ABCDEFGH A;B B:C D:E F G