Question: Using the PERT method review the following data for a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES ( DAYS ) ACTIVITY a

Using the PERT method review the following data for a project that should be scheduled using CPM:
IMMEDIATE PREDECESSORS TIMES (DAYS)
ACTIVITY a m b
A 147
B 3510
C A 258
D A 4611
E B 123
F C,D 357
G D,E 126
H F,G 256
b. What is the critical path?
multiple choice
A-C-F-H
A-D-G-H
A-D-F-H
B-E-G-H
c. What is the expected project completion time? (Round your answer to 3 decimal places.)
Project completion time
days
d. What is the probability of completing this project within 22 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!