Question: Using the PERT method review the following data for a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b
Using the PERT method review the following data for a project that should be scheduled using CPM:
| IMMEDIATE PREDECESSORS | TIMES (DAYS) | |||
| ACTIVITY | a | m | b | |
| A | 1 | 2 | 6 | |
| B | 1 | 2 | 9 | |
| C | A | 2 | 2 | 11 |
| D | A | 1 | 8 | 9 |
| E | B | 1 | 2 | 3 |
| F | C,D | 3 | 4 | 11 |
| G | D,E | 1 | 3 | 11 |
| H | F,G | 2 | 3 | 11 |
b. What is the critical path?
B-E-G-H
A-D-F-H
A-D-G-H
A-C-F-H
c. What is the expected project completion time? (Round your answer to 3 decimal places.)
d. What is the probability of completing this project within 19 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.)