Question: Using the PERT method review the following data for a project that should b e scheduled using C P M : IMMEDIATE PREDECESSORS TIMES (

Using the PERT method review the following data for a project that should be scheduled using CPM:
IMMEDIATE PREDECESSORS TIMES (DAYS)
ACTIVITY amb
A-147
B-2613
CA114
DA234
EB246
FC,D159
GD,E129
HF,G369
b. What is the critical path?
multiple choice
B-E-G-H
A-D-F-H
A-D-G-H
A-C-F-H
c. What is the expected project completion time? (Round your answer to3 decimal places.)
Project completion time days
d. What is the probability of completing this project within 20 days? (Do not round intermediate calculations. Round your answer to4 decimal places.)
Probability

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!